If you run post-closure care on a capped cell, you already have a set of settlement monuments out there somewhere, usually a steel rod driven down to a stable layer, sleeved so the waste mass can move around it, with a brass cap or a short section of pipe sticking up at grade. A survey crew shoots each one with a level or an RTK rover on a schedule your permit spells out, logs the elevation, and compares it to the last reading and to the baseline set when the cell was certified closed.
That's the whole instrument. No electronics, no battery, no data feed. Just a fixed point and a number that changes a little bit every time someone measures it.
Why the reading happens on a schedule at all
Waste settles. Organic material decomposes, voids collapse, the whole mass compresses under its own weight and under the cap material sitting on top of it. That settlement isn't uniform. Thicker areas of old municipal waste settle faster than a thin lift near the perimeter, and a cell built over several phases can have one corner still dropping an inch a year while the rest has gone flat.
Your permit cares about the rate, not the raw number. Most post-closure plans require monitoring on a set interval, often quarterly in the early years, because that's the cadence regulators settled on for catching a settlement rate that's still trending down toward the threshold where care obligations can eventually be reduced. Space the readings too far apart and you lose the ability to tell a normal decay curve from a cell that's stalled out or started moving again after a period of looking stable. Space them too close and you're paying a survey crew to confirm what you already knew last month.
The quarterly cadence also lines up with the things settlement actually causes: a low spot that collects water after a storm, a grade that's gone flat enough to pond instead of sheet-flow runoff, a seam where the cap has pulled apart enough to show at the surface. Those problems show up weeks or months after a settlement trend crosses some threshold. A reading interval wider than a few months leaves you explaining a ponding complaint to the state before your own survey data has caught up to it.
What the monument data doesn't tell you
A settlement monument tells you what happened at one point, directly above itself, since the last visit. It says nothing about the three acres between monuments, and most cells only have a handful of them spaced along the perimeter and a few interior transects because that's what the original design called for and what the budget allowed.
That gap matters because settlement and cover failure don't always show up at the same spot. A monument near the toe of the slope can read perfectly flat for years while a differential settlement crack opens up fifty feet away, between two monument locations, in an area nobody's shooting. By the time that crack is visible on the ground, often as a stressed strip of vegetation where root zones have been disturbed or where ponding has killed off the grass cover, it's already a repair line item instead of a watch item.
Settlement monuments and vegetation condition are reading two different signals from the same underlying cause. One tells you the elevation changed. The other, read across the whole cap instead of a handful of fixed points, can show you where the surface is already reacting to a problem the monuments haven't caught yet because there isn't one sitting nearby.
If you're already pulling quarterly survey data from your monuments, pairing it with a quarterly vegetation read across the whole capped cell gives you a second data set that covers the ground between the points your rod and cap can't reach. We're running that as an early pilot right now, and we're looking for post-closure sites willing to try it alongside their existing monitoring.